Formwork

 Permanent Formworks
   

Permanent formworks are part of the permanent structure of the building. The main advantages are that they save time and labour as there is no need to dismantle the formwork. They reduce costs and save time by (source: CIRIA C558):

· Reducing the skill level needed on site.
· Increasing the potential for standardisation and repetition.
· Permitting off-site fabrication in factory conditions followed by scheduled and
   appropriate deliveries.
· Speeding up erection times, particularly in building works.
· Eliminating the need to strike formwork and falsework.
· Allowing early access for following or concurrent operations.
· Eliminating the programme limitations of reuse of formwork.

The use of permanent formwork can reduce construction and maintenance costs, shorten construction time, and improve safety by reducing hazards during construction. It also reduces construction waste generation during construction.

Maintenance costs are reduced by:

· Improving curing of concrete and reducing shrinkage craking.

· Ensuring adequate cover to the reinforcement and providing associated benefits
   such as increased resistance to chloride ingress and carbonation, where appropriate.

· In many instances improving the durability of the structure.

· Providing the decorative finish required.

 
Definitions

Permanent formwork is a structural element that is used to contain the placed concrete, mould it to the required dimensions and remain in place for the life of the structure.

Participating permanent formwork makes some predetermined contribution to the strength of the structure.

Non-participating permanent formwork makes no strength contribution but may provide additional benefits such as improved durability, finish or insulation properties.

Potential applications and benefits of permanent formwork (source: CIRIA C558):

 

Checklist of recommended applications of materials for permanent formwork

Description of some permanent formwork.

 

METTALLIC
 

Profiled steel

The major use is in the high rise steel frame building sector where its speed of erection proved to be a great asset.
 
Common usage:
bullet

Composite beam and slab type concrete floors with the formwork spanning between either steel or concrete beams.

bullet

Ribberd floors within the depth of the permanent works supporting members.

 

Span Range:

bullet

Typical maximum span indicated is based on a150 mm slab.

bullet

Trapezoidal sections permitting a simple or multiple span of 1.5 to 3.8m for 1.2mm sheet thickness.

bullet Trapezoidal section designed for use in slim floor systems permit spans of up to 6.5m unpropped and 9m propped.
bullet Re-entrant sections permitting a simple or multiple span of 2.0 to 5.5m for 1.2mm sheet thickness
 
Advantages:
bullet Economies of cost and speed over traditional methods.
bullet Improves safety in difficult situations by providing a safe working platform and cover for other trades.
bullet Large span range.
bullet Light and easy handle.
bullet Stiffens supporting steel frame.
bullet Easily cut and fitted to awkward shapes.
bullet Sealing between panels can be provided by lapping edges and ends.
 
Disadvantages:
bullet Access or ribbed profiles difficult when in position.
bullet Can compromises reinforcement detailing if used in bridges works.
bullet The exposed steel sheet providing the tensile reinforcement is susceptible to fire damage and additional reinforcement may be needed in the slab to provide adequate fire resistance.
   

Coated mesh

A variation on a small open mesh is the use of larger, structural steel mesh with an additional coating to retain the concrete.
 
Common usage:
bullet

For below ground structures such as ground beams, column bases and pile caps.

bullet

External support provided by backfill to structure.

bullet

Can be used in above ground applications if external support is provided by either temporary falsework or standard lattice type walings and through ties.

 
Advantages:
bullet Lower cost and higher speed over traditional methods.
bullet Light and easy to handle.
bullet Easily cut and fitted to awkward shapes by unskilled labour.
bullet Reduces overdig, consequent backfilling and spoil removal.
 
Disadvantages:
bullet Requires phased reinforcement fixing and backfilling.
bullet Care needed during backfilling to prevent distortion and consequent loss of cover.
bullet Large footprint spacer blocks required to prevent puncture of the polyethylene coating.
bullet Links must be detailed and fixed to take backfill loads.

 
Examples in Hong Kong
Concrete Permanent Formwork
Semi-Precast slabs
bullet

The Cambridge House, Quarry Bay.

bullet

The Rosedale on the Park Hotel, Causeway Bay.

Metal Permanent Formwork
Staircases
bullet

The Charter House, Central.

 

   
 

 

Steel mesh

Steel mesh can be used as permanent formwork, generally in vertical applications, with either a small opening, similar to largest aggregates size, to retain the placed concrete directly or as a larger size mesh with additional coating.

 

Common Usage as permanent formwork:

bullet

Construction joints in slabs.

bullet Deep construction joints.
bullet Vertical construction joints to walls.
bullet Wall and column formwork, for further finishing or rendering.
bullet Soffit formwork.
bullet Curved wall formwork.
bullet Arch formwork.

 

Span Range:

bullet At the base of thick walls and deep stop ends supports at 225 to 325mm centers, depending on thickness.
bullet Shallow stop ends 675 to 725mm for 500mm slab depending upon thickness.
bullet For soffit of 300mm slab supports at 425 to 575mm depending upon thickness.
 

 

Advantages:
bullet Economies of cost and speed over traditional methods.
bullet Light and easy to handle.
bullet Easily cut and fitted to awkward shapes by unskilled labour.
bullet Benefits can be taken of reduced formwork pressures when using expanded mesh.
bullet Pour can be monitored from partially exposed face.
bullet Continuity of reinforcement through stop ends can readily be accommodated.
 
Disadvantages:
bullet Produces an unformed face which is acceptable for stop ends to receive further concrete but must be rendered/faced for a fair finish.
 
CEMENTITIOUS
   
Concrete
Lattice products
Precast concrete panels up to 2400mm wide reinforced by welded lattices which project into, and provide a mechanical linkage with, the in-situ concrete slab.
   
Common usage :
bullet

Composite concrete floors spanning between either steel or concrete beams.

bullet

Composite bridge decks spanning between either steel or concrete beams.

 
Span Range :
bullet Up to approximately 3.8m for self-supporting units.
bullet Larger spans, up to 10m, will require propping at construction stage.
bullet Longer panels are available for particular applications.
 
Advantages:
bullet Lower cost and higher speed over traditional methods.
bullet Large areas quickly placed with mechanical handling.
bullet Large span range.
bullet Compatible material.
bullet Can simplify reinforcement detailing, particularly when used in building works.
 
Disadvantages:
bullet Relatively heavy, will require some mechanical handling.
bullet Access difficult when in position, will require the provision of access routes.
bullet Can compromises reinforcement detailing, particularly when used as planks in bridgeworks.
bullet Tolerances of panels and permanent works, creep during positioning.
   
Attention
To minimize demolition waste and provide maximum recycling opportunities, the use of permanent formwork should be carefully considered. Permanent formwork using different material types may be difficult to recycle.
 

 

 
Large Panel Formwork
 

Large panel formwork consists mainly of large pieces of metal formwork. It is most suitable for construction activities where formwork is highly repetitive as it can be reused many times. Therefore, its design is specified for the construction of the load bearing walls of typical floors in high rise tower blocks.

 

Compared with traditional timber formwork, metal panel formwork has several advantages. The use of large panel formwork can save time and labour in erecting, striking and re-erecting the formwork as the panel is handled as one unit. It can also produce a concrete surface, which is neater than is produced normally by conventional timber formwork, and the surface essentially needs no additional applied finishes for levelling. On site waste audit records also show large panel formwork systems are effective in reducing concrete waste generated by losses due to damaged formwork, which usually accounts for 30% of the total concrete waste. However, because of the weight of large panel formwork, tower cranes should be available for its handling.

 

       

 

Large panel formwork

 

Removal of formwork

 
 

Different large panel formwork systems are widely used today by contractors for constructing standardised housing blocks, and are broadly classified as wall forms, table forms and tunnel forms.

 
Wall Forms
 

The wall forms are combined with the slab form so that the wall and slabs can be formed monolithically in one casting operation, and the number of joints between panels is minimised. There is less chance of grout leakage or an uneven surface finish at the joint, which is a common fault with in traditional timber formwork.

 
Table Forms
 

Standard modules of housing blocks are relatively large in span and large table forms are widely used for assembly time reduction, fewer joints and better surface finishes. The table method uses separate vertical forms for walls and horizontal table forms for floor slabs. The work is done in two stages. First, the walls are cast, and forms are stripped, the tables are then positioned, and the horizontal slabs are cast.

 
Tunnel Forms
 

The half tunnel is composed of vertical and horizontal panels set at right angles and supported by struts and props. The walls and slabs are cast in a single operation. Like the wall-forms and table forms, this reduces not only the number of joints, but also the assembly time. Therefore, the casting of walls and slabs can be completed in the one day.

 
Steel Forms
 

Because steel forms are very durable, one set of steel forms can be used to complete a project, and then reused for another project or scrapped for recycling. Steel forms can produce a better quality concrete finish when compared with timber forms. Although their initial cost is higher, they can be cheaper in the long run, particularly with their recycling potential.

 
Composite Steel Decking
 

Steel decking, becoming a permanent part of a composite slab, serves as both the working platform and formwork for supporting the in-situ slab concrete in the construction stage. The steel of the decking can also utilised to provide some of the required permanent reinforcement for the slab. In other words, the decking can replace both timber formwork and bottom reinforcement, reducing the amount of temporary works and formwork required.

 
Aluminum Forms
 

Aluminum formwork consists of small aluminum framed panels which are easy for handling. It is fast to erect and strike and the floor cycle can be 4 days. It is durable and can be reused over 100 times. Although it is more expensive than steel and timber, its merit is its lightweight and recycling potential.

 
Plastic Forms
 

PVC and polyurethane forms can be used to replace timber forms in either rigid or flexible formats. Special floor forms made of fibreglass are occasionally used (6%). They can be reused over 50 times and produce a concrete surface finish similar in appearance to fine snake skin. If a smooth finish is desired, a paste wax or water-based release agent can be applied to the form.

 
Rib Loc Circular Column
 

This UPVC form is usually used to cast circular columns of diameter ranging from 150 to 3000mm. It is made by spirally winding a ribbed plastic profile into a tube. This enables column forms to be constructed which are strong, lightweight, easy to strip and which provide an excellent surface finish. The surface also incorporates the inherent “waxiness” of extruded plastic and no form oil is required. Square stabilisation timbers are fixed at the foot of the column formwork to stop the formwork moving out of position. Vertical bracing timbers are placed against possible movement while concreting. The process is cost efficient with recycling potential.

 

        

 

UPVC column forms

 

Erection of column forms

 
 
Pecaform
 

This is made by laminating a layer of polyethylene to each side of a high tensile steel wire mesh. This combination creates a material that is both light and structurally strong, making it very easy to handle. It can be used for constructing ground beams, pile caps, footings, curved structures, ribbed and waffle slabs. The formwork is cut-to-size and bent to shape at factory and arrives at site ready for installation. There is no need to strip formwork after the concrete has cured. No waste is produced. A clean and neat site can be obtained in the foundation stage with Pecaform.

 

Construction of pile caps using Pecaform

 

Backfill around pile caps about 150mm from the top level of Pecaform

 
High Density Overlaid (HDO) Plywood
 

The coating of conventional plywood with a thick layer of polymer resin may improve the quality and durability of the formwork. For example, applying a medium density overlay or a high density overlay on plywood can increase the number of reuses to 20. The form can be easily dismantled and handled by small cranes and can be adjusted to suit architectural requirements.

 
Example Supplier for Aluminium Formwork
 
VSL Hong Kong Limited
3/F Stelux House, 698 Prince Edward Road East, San Po Kong, Kowloon, 
Hong Kong.
Tel: (852) 2590 2288
Fax: (852) 2590 0290
 
Example Application for Steel Formwork
 
Cheung Sha Wan West Phase-II, Hong Kong
 
Proposed Redevelopment Oxford House at Quarry Bay, Hong Kong
 
Proposed Residential Development at 5-7 Blue Pool Road, Happy Valley, Hong Kong
 
Residential Development at Aldrich Bay Reclamation, Shau Kei Wan, Hong Kong
 
Sau Mau Ping Estate Redevelopment Phase-V, Hong Kong
 
Shek Yam Estate Phase-III, Hong Kong
 
Tseung Kwan O Area 73A Phase-II, Hong Kong
 
Tseung Kwan O Area 74 Phase-IV, Hong Kong
 
Example Application for Aluminium Formwork
 
Proposed Residential Redevelopment at I.L. 8290 Stubbs Road, Hong Kong
 
Residential Development at Aldrich Bay Reclamation, Shau Kei Wan, Hong Kong
 
Shek Yam Estate Phase-III, Hong Kong
 
T.K.O.T.L. No.55 Tseung Kwan O Phase-I, Hong Kong
 
Tseung Kwan O Area 73A Phase-II, Hong Kong
 
Tung Chung Station Development Package One, Site 3, Hong Kong
 
Example Application for UPVC Formwork
 
Proposed Residential Development at 5-7 Blue Pool Road, Happy Valley, Hong Kong
 
Tung Chung Station Development Package One, Site 3, Hong Kong
 
     

Low-Waste Buildings Technologies & Practices
Home