|
|||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||
|
Charter Road, Charter House (Update) |
||
Overview |
||
This project involves construction of a 28-storey Grade A office space and three floors of luxury retail accommodation. The structure was constructed on a 6-day cycle. |
||
Composite Staircases | ||
The stairs came as 200 kg galvanized metal boxes with risers and reinforcing bars already in place. This system saves the need to construct and dismantle formwork. Superficially the method seemed more expensive than traditional in situ construction using timber formwork, but the cost actually worked out the same because it produced a good surface finish in less time, which meant the contractor did not have to spend time and money on remedial works (source: The Journal of The Hong Kong Institution of Engineers, June 2002). |
||
Table Form | ||
Each table form measured about 12m by 3-4m and 41 tables were used for each quadrant of the slab. The tables are small enough to be handled by three to four man each. | ||
. | ||