Process |
Traditional
Methods |
Low-Waste Technologies |
Building Design |
![](../icons/bullet.gif) |
Use of materials size does not correspond with the dimensions in
the building |
![](../icons/bullet.gif) |
With the standard modular approach, walls and slabs are standardized
in both size an shape, being interchangeable between different
building types |
|
![](../icons/bullet.gif) |
Building
components not standardized |
![](../icons/bullet.gif) |
Standardized
building components |
|
![](../icons/bullet.gif) |
Down-stand
beams and columns detrimental to large panel formwork system
construction |
![](../icons/bullet.gif) |
Walls
and flat slabs only, no down-stand beams and columns |
|
![](../icons/bullet.gif) |
Specifications
exceed the performance required |
![](../icons/bullet.gif) |
Modification
of specifications to suit the contractor’s available equipment and
materials |
|
![](../icons/bullet.gif) |
Significant
unnecessary mid-project variations |
![](../icons/bullet.gif) |
Less
design variation |
Formwork |
![](../icons/bullet.gif) |
Conventional timber formwork |
![](../icons/bullet.gif) |
Large steel panel forms |
|
![](../icons/bullet.gif) |
Double
the cost of using steel panel in long run |
![](../icons/bullet.gif) |
High
initial cost but balanced by the long terms savings in timber
formwork |
|
![](../icons/bullet.gif) |
Labour
intensive for erecting and striking formwork |
![](../icons/bullet.gif) |
Less
labour force required for erecting and striking formwork |
|
![](../icons/bullet.gif) |
Longer
construction duration |
![](../icons/bullet.gif) |
High
efficiency, twice faster than timber formwork system |
|
![](../icons/bullet.gif) |
Plastering
need for leveling concrete surface |
![](../icons/bullet.gif) |
Better
quality concrete products, concrete surfaces suitable for applying
tiles and paints directly |
|
![](../icons/bullet.gif) |
Reused
8-15 times, several sets of timber forms needed for a high-rise
block |
![](../icons/bullet.gif) |
Reused
over 100 times, one set of forms sufficient to complete a block and
can be reused in another sites |
|
![](../icons/bullet.gif) |
Hand
lift timber board from floor to floor |
![](../icons/bullet.gif) |
Tower
cranes needed for lifting formwork |
|
![](../icons/bullet.gif) |
Considerable
timber waste produced |
![](../icons/bullet.gif) |
Waste
steel scrapped for recycling, less waste produced |
Concrete Work |
![](../icons/bullet.gif) |
In-situ placement |
![](../icons/bullet.gif) |
Precast concrete |
|
![](../icons/bullet.gif) |
Time
consuming |
![](../icons/bullet.gif) |
Shorter
construction time |
|
![](../icons/bullet.gif) |
Higher
labour cost |
![](../icons/bullet.gif) |
Higher
initial cost but relative cheaper for large quantity |
|
![](../icons/bullet.gif) |
Poor
quality, honeycombing often occurs |
![](../icons/bullet.gif) |
Mass
production, high degree of quality control |
|
![](../icons/bullet.gif) |
Plastering
required before applying tiles and paints |
![](../icons/bullet.gif) |
Elements
usually completed with necessary fixtures and finishes, no need for
further finishing works |
|
![](../icons/bullet.gif) |
More
waste produced |
![](../icons/bullet.gif) |
About
30% less waste than in-situ concreting |
Masonry Work |
![](../icons/bullet.gif) |
Brick walls or concrete block walls |
![](../icons/bullet.gif) |
Internal drywall partitions |
|
![](../icons/bullet.gif) |
Lower
materials cost but higher labour cost |
![](../icons/bullet.gif) |
Higher
materials cost but lower labour cost |
|
![](../icons/bullet.gif) |
High
skill levels |
![](../icons/bullet.gif) |
Easy
to install, low skill levels |
|
![](../icons/bullet.gif) |
Thick
layer of plaster needed |
![](../icons/bullet.gif) |
Smooth
surface and no plastering needed |
|
![](../icons/bullet.gif) |
Time
consuming |
![](../icons/bullet.gif) |
Four
times faster than masonry work plus plastering |
|
![](../icons/bullet.gif) |
More
waste produced |
![](../icons/bullet.gif) |
Wet
trade not involved, hence less waste generated |
|
![](../icons/bullet.gif) |
Walls
with higher strength |
![](../icons/bullet.gif) |
Walls
with lower strength |
Plastering |
![](../icons/bullet.gif) |
Conventional mortar cement |
![](../icons/bullet.gif) |
Spray Plaster |
|
![](../icons/bullet.gif) |
Manual
Applying |
![](../icons/bullet.gif) |
Mechanical
spraying |
|
![](../icons/bullet.gif) |
Suitable
for rough wall surface, further leveling is required |
![](../icons/bullet.gif) |
Suitable
for smooth wall surface, further leveling is not required |
|
![](../icons/bullet.gif) |
Time
consuming |
![](../icons/bullet.gif) |
Faster
construction |
|
![](../icons/bullet.gif) |
Labour
intensive |
![](../icons/bullet.gif) |
Less
labour demand |
|
![](../icons/bullet.gif) |
More
waste generated |
![](../icons/bullet.gif) |
Less
waste generated |
Hoarding |
![](../icons/bullet.gif) |
Timber hoarding |
![](../icons/bullet.gif) |
Steel hoarding |
|
![](../icons/bullet.gif) |
Cheaper
materials cost, easy to erect |
![](../icons/bullet.gif) |
Expensive
and demand higher labour force for erection, but safe for passer-by |
|
![](../icons/bullet.gif) |
Less
durable, about 2 years lifetime |
![](../icons/bullet.gif) |
More
durable, about 4.5 years lifetime |
|
![](../icons/bullet.gif) |
Low
reusability, discarded after used once |
![](../icons/bullet.gif) |
High
reusability, waste steel scrapped for recycling |
|
![](../icons/bullet.gif) |
More
timber waste produced |
![](../icons/bullet.gif) |
70%
less waste |
Scaffolding |
![](../icons/bullet.gif) |
Conventional bamboo scaffold |
![](../icons/bullet.gif) |
Gondola with Passenger Lift |
|
![](../icons/bullet.gif) |
Lower
initial cost |
![](../icons/bullet.gif) |
Higher
initial cost, but balanced by saving in materials cost in the long
run |
|
![](../icons/bullet.gif) |
High
labour cost |
![](../icons/bullet.gif) |
Less
labour force required |
|
![](../icons/bullet.gif) |
Less
safe for workers |
![](../icons/bullet.gif) |
More
safe for workers |
|
![](../icons/bullet.gif) |
More
bamboo waste produced |
![](../icons/bullet.gif) |
80%
less waste |