Case Studies

 

Ocean Shores Phase 3, TKOTL 55, Tseung Kwan O

 

   

For more information, please refer to the existing case study: TKOTL 55 Area 72, Tseung Kwan O, in the low waste building technology web site:
www.cse.polyu.edu.hk/~cecspoon/lwbt/case_studies/TKOTL_55/TKOTL_55.htm

 

Notable Features

Operation Procedure of the Climbing Scaffolding

.
Basic Information Cost Comparison .
Overview Contact of Contractor .
Comparison of Construction Programme Sources .
Notable Features
bullet Climbing scaffold system
Basic Information
Location :
Tower 16 & 17, TKOTL 55, Tseung Kwan O
Building Type :
Residential
Contract Period :

14 months, from August 2001 to October 2002

Contract Sum :
HK$9,1M
Developer :
Swire Properties Ltd.
Project Manager :
Calm Seas Project Management Limited
Architect :
Wong Tung & Partners Ltd.
Structural Engineer :

Joseph Chow & Partners Ltd.

E&M Consultant :
Meinhardt (M&E) Ltd.
Quantity Surveyor :
Davis Langdon & Seah Hong Kong Ltd.
Main Contractor :
Sanfield Ltd.
.
Overview
 

Ocean Shores tower 16 & 17 development, is part of a residential complex with a site area over 500,000 square feet. A three level podium structure provides facilities such as a clubhouse, a swimming pool, tennis courts, children’s playground, car park, etc.

 
 
Comparison of Construction Programme
 
 
(refer to figure)
 
Cost Comparison
 
 
(refer to figure)
 
Contact of Contractor
 

Sanfield Building Contractors Ltd.
44/F
Sun Hung Kai Center,
30 Harbour Road, Wanchai, Hong Kong.
Tel: (852) 2827 8111

Fax: (852) 2827 0717

 
Sources
 
bullet Wui Fai Holdings Ltd., World Pacific Scaffolding Works Ltd., climbing scaffolding presentation.
bullet Ocean Shores web site: www.oceanshores.com.hk
 
 
   
Operation Procedure of the Climbing Scaffolding
- Rendering works commencing.
- Support brackets installation for base frame
  erection.
- After completing the external wall, tiles for
  mock-up floor (1/F to 3/F).
- Scaffolding B climbing 8 floors upper external
  wall rendering works.
- Erecting the 2nd catch fans for climbing
  scaffolding B.
- 3rd operation upward for climbing scaffolding
  B.

- Erecting the non-typical floors, LMR, U/R &
  T/R by traditional bamboo scaffold system.

- 4th operation upward for climbing scaffolding
  B.
- Erecting the 3rd catch fans at 27R level.
   
- Climbing scaffolding B were operated-up to
  43/F for external wall rendering works and
  then operating-down to 27R/F-35 for
  external wall tiling.
- 36/F-53/f external wall tiling will be laid
  through by climbing scaffolding A.
- 1st operation downward for climbing
 
scaffolding B.
- Removing the catch fans at 27R level.
- 2nd operation downward for climbing
  scaffolding B.
- Bamboo scaffolding to be removed upon the
  completion of cleaning works for external wall
  tiling at T/R, LMR and U/R.
- Removing the catch fans at 15/F level.
- 3rd operation downward for climbing
  scaffolding B.
- Removing catch fans at level 3/F.
- Finally remove the climbing scaffolding A and
  supporting brackets for making-good the
  finishing of the transfer plate.
- Removing the climbing scaffolding A like removing B.
 