Loss-form Construction System |
Precast lost
form panel and corner unit are used for the facades. The loss-form precast
panels for the façade are used as permanent formwork together with aluminum
formwork for the inside. The loss form panel is made of precast concrete and
cladding at the factory and transported to the site. Tile filet is used for the
installation of tile grout. The construction sequence is as shown in the
figures: |
|
|
|
1.
Lost form
panel lifted to designate
location. |
2.
Brace lost
form panel with kicker. |
3.
Erect intend
wall and slab
formwork. |
4.
Pour wall,
slab and beam concrete. |
|
|
|
The loss form
panel dimensions are: 75mm thickness, and 2,534 high. |
|
The loss form
corner units are: 450mm x 550mm. |
|
|
This system
minimizes the use of aluminum formwork for the external side, as it is a
permanent formwork used as façade precast concrete cladding. Also the generation
of waste on-site is reduced. |
|
|
Precast facades and
Semi-prescast Balconies |
The precast
facades are manufactured in China and transported to the site, stored in a
storage area and lifted with a crane to the final position. Two types of precast
facades are used in this project: type A, corner unit with external sun shading
device, and type B with two window façade units. Type A precast façade is
installed next to type B precast façade. Neoprene and metazeal was installed
between the precast facades. |
|
|
|
Semi-precast
balconies
Semi-precast balconies are also manufactured in China and transported to the
site for installation. After installing the drainage system, concreting and
finishes are applied. |
|
|
|
|
Aluminum System
Formwork
(Slab, Beams and Loss-form) |
Aluminum
formwork was used for on side of the loss-form system and for the beams and slab
construction. Aluminum formworks are easy to handle and can be reused over 100
times, and recycled after being reused. |
|
|
Hardiwall Partitions |
The hardiwall
solid wall system reduces waste generated on-site as no wet trades are involved.
It reduces structural design requirements due to lighter weight wall
construction, and increases floor space due to thinner walls. Also it is up to 3
times faster to install than masonry wall. |
|
|
Spray-on-plaster |
Spray-on
–plaster has advantages such as high productivity, low labour demand and less
waste generation. |
|
|
Contact of
Contractor |
Hip Hing
Construction Co. Ltd.
29/F New World
Tower
16-18 Queen’s Road Central
Hong Kong
Tel:
(852) 2525 9251
Fax:
(852) 2845 9295
www.hiphing.com.hk |
|
|