Case Studies

 

Proposed Residential Redevelopment at Nga Tsin Wai Road

 

Notable Features
 
bullet Application of Metal-Bamboo Matrix System Scaffold
bullet Use of timber formwork
bullet On-site sorting of waste
bullet Reuse of steel hoarding
bullet Use of Gypsum base spray plaster
bullet Use of Auro paint 

Basic Information
 
bullet Location: Kowloon City
bullet Building Type: Residential 
bullet Contract Period: 315 days
bullet Gross Floor Area: approx. 2780m2
bullet Client: Globpcc Development Ltd.
bullet Architect: P&T Architects and Engineers Ltd.
bullet Structural Engineer: P&T Architects and Engineers Ltd.
bullet E&M Consultant: P&T (M&E) Ltd.
bullet Quantity Surveyor: Levett & Bailey Chartered Quantity Surveyors
bullet Main Contractor: Hsin Chong Construction (Asia) Ltd.
bullet Contract Sum: HK$ 73,500,000

Overview
 

The Works comprised the construction of 6 residential units, each with a 5 storey height. The substructure comprised reinforced concrete columns and walls, ground beams and slabs. The superstructure was of reinforced concrete walls, columns, beams, staircases, suspended slabs and ramps. The external walls were of 100mm reinforced concrete finished externally with granite tiles and plaster. The internal partitions were generally of 100mm solid concrete block. The windows were generally of fluorocarbon aluminum frame and glazed with clear or obscured glass. The roofs were covered with asphalt on reinforcement cement and sand screed and finished with precast concrete tiles.

 

  Waste Management
   
  bullet On-site sorting of waste
   
  There was shortage of site space to install refuse chute. Waste materials were transported to the ground level by labourers or by tower crane. During the concreting stage there was no sorting of waste performed. Waste material in form of a mixture of rubble and small piece of timber was packed in bags and transported to the ground level by labourers. If sorting was to be performed, a large number of labourers would be required. During the finishing stage, cement, PVC, tile and packaging waste material were sorted out in bags and transported to the ground level either by labourers or by tower crane.
   
  bullet Material Control
   
  For reinforcement and tiles where the materials were supplied by the main contractor, a bonus scheme was adopted to encourage the sub-contractor to minimise the wastage of material. Normally, 5% of wastage was allowed. A mock up flat was also used to estimate the quantity of tiles required. All material waste was minimised by close supervision.
   
  bullet  Use of recycled materials
   
 
bullet Gypsum base spray plaster

bullet

Auro paint
   
  bullet

Reusable materials

   
 

bullet

steel hoarding

 

   
Timber Formwork
 

Timber formwork was used for this project due to the following reasons:

 
bullet There were several fins on the external walls.
bullet Tight programme and the low-rise blocks was to be constructed simultaneously.
bullet Lack out storage space for the steel formwork.
 

Metal-Bamboo Matrix System Scaffold
 
A new and systematic scaffolding ‘Metal-Bamboo Matrix System Scaffold’ was used for this project. The principal is the combination of both the characteristics of metal scaffolding and bamboo scaffolding. It comprises of steel pipes (60%) and bamboo poles (40%). All posts and ledgers are constructed with metal tubes. All braces are also metal tubes connected by clamps at 60o subjected to different site situation.
 
Metal-Bamboo Matrix System Scaffold is composed of two layers similar to the traditional metal or bamboo scaffolding. For the outer layer, metal tubes are used as the main posts and main ledgers for maximum support, while bamboo is used as guardrail and fencing to minimise the loading and to increase its flexibility. For the inner layer, bamboo is used in areas with the transoms.
 

Together with other components, such as catwalks, toeboards and staircases, provides stable and safe working environment and accesses for workers working on it. The catwalks are made of aluminum while the toeboards are made of plastic. These materials can be reused and help to save the timber waste.

 

 

 

As for cost comparison, is about 15% higher than traditional bamboo scaffolding. The following table shows the comparison  with traditional steel scaffolding and traditional bamboo scaffolding.

 

 

Traditional steel scaffolding

 New System

Traditional bamboo scaffolding

Catwalk

yes

yes

no

Toeboard

yes yes no

Stair access

yes yes no

High reliability

yes yes no

Flexibility

no yes yes

Light weight

no yes yes

High productivity

no yes yes

Minimum of costs

no yes yes
 

Contact of Contractor
 
Hsin Chong Construction (Asia) Ltd.
Hsin Chong Center, 107-109 Wai Yip
Street, Kwun Tong, Kowloon
Tel: (852) 2579 8238
Fax: (852) 2516 9430
 

 

Low-Waste Buildings Technologies & Practices
Home